Flower Circle Reconstruction

On May 18, 2021, the City Council adopted Resolution No. 2021-44, awarding the first phase of the Annual Resurfacing Project to Don Chapin Company to reconstruct Flower Circle. The method of reconstruction is a sustainable construction method called Full Depth Reclamation (FDR).

Construction is scheduled to begin on July 15, 2021 and will take 30 working days to complete. The project schedule can be downloaded here.

Full Depth Reclamation transforms the existing asphalt pavement and underlying granular material into a stabilized base for a new pavementFDR Sample surface layer. This process saves on the cost of removing & replacing the pavement surface, reduces the required truck trips removing and importing materials, and provides a higher structural strength than normal roadway baserock.